This task is the first one of the application. ETA ~end august/early september
Project review log
Log of 25th August Project Review
Planning
Task | week 1 11th november 16th november |
week 2 17st november 23th november |
week 3 24th november 30th november |
week 4 1 december 7th december |
Status | Comments |
---|---|---|---|---|---|---|
Verify it works on Mac Linux Windows Solaris | OK | done | ||||
Verify the crashes are fixed (see relevant issues) | working on it | |||||
Write report for task 1 | began |
Task | week 1 14th july 19th july |
week 2 21st july 26th july |
week 3 28thjuly 2nd august |
week 4 4th august 9th august |
week 5 11th august 16th august |
week 6 18th august 23th august |
week 7 25th august 30th august |
Status | Comments |
---|---|---|---|---|---|---|---|---|---|
Check the sources (one milestone) | ok | ||||||||
Understand how cvs manages the sources ( CVS dirs) | ok | ||||||||
Configure step : find information, be able to modify configure.in | ok | ||||||||
Understand the bootstrap | ok | ||||||||
Build mozilla archive separately | ok | ||||||||
Fix a build issue (bad compiler option maybe) | ok | ||||||||
Understand how patches are used at buildtime | ok | done | |||||||
Modify the makefile, and start building seamonkey ( basic patch provided ) | done | ||||||||
Define a strategy for the migration | done (cleanup in progress) | ||||||||
Modify configure (replace mozilla checking with seamonkey checking) | OK | holidays | |||||||
Apply the changes progressively ( and propose tests for the QA) | OK | holidays | OK | ||||||
Project Reviews | First project review Done |
||||||||
Propose patches to commit the changes in a cws | holidays | done | |||||||
Verify it works on other ports ( Mac OS X , windows ) | holidays | work in progress | |||||||
Verify the crashes are fixed (see relevant issues) | |||||||||
Write report for task 1 |
- Create a Gantt diagram / Planning
- ....